So with the preparatory work done, official date of commencement (contract stuff) was
Tuesday 25 July. That means (also contract stuff) that the date for practical completion is 19 February 2018... 210 days from 25/7/2017. With a bit of luck, it might be a tad earlier... here's hoping.
|
When the portaloo arrives, you know it means business |
|
Brickies busy laying the 3 courses up to slab level |
|
If you've got to work, its not a bad spot |
|
The view from the alfresco area.... imagine garden instead of soil & a glass of bubbles in hand....... |